Concrete Improvements
Kraft Heinz - Fremont, OH
IPS has an ongoing relationship with Kraft Heinz working on mechanical, electrical, and general construction projects. Our team completed all the sitework & concrete for a new entrance to the distribution center, parking lot improvements, and new guard house/security area.
As the sun came up over the Kraft-Heinz Distribution Center (see above picture), the IPS Civil group began to grind through the first day of a 1,030 CY total concrete pour (41,000 SF) to be completed in three consecutive days. This project was initiated in efforts to change the flow of traffic at the customers facility to create a safer work environment.
- 1,030 Cubic Yards of concrete poured
- Bid Build delivery method
- $1.1 million project value
- 41,000 SF size of site