Project Scope:

Sunoco was required to upgrade its pipeline to meet US Department of Transportation requirements. The pipeline runs from the barge off-loading facility at the Port of Toledo to Sunoco’s tank farm in Oregon, Ohio. IPS upgraded the piping, pumps and offloading stations to meet all DOT protocol and requirements.

 

Challenges:

The Sunoco pipeline runs thru the Sunoco refinery in Oregon Ohio. All repairs to the pipeline were required to be made in conjunction with the Sunoco operational permitting processes. This includes daily permits for all hot work and enhanced safety protocol.

IPS
$800,000 Total Construction
N/A Project Cost
6/2012 Completion Date
6 Project Duration
Design Bid Build Delivery Method

Project Scope:
IPS and ANR Pipeline negotiated a Master Service Agreement for the maintenance and improvement of site facilities, boilers and piping at the ANR Defiance compressor station.
Specific projects include:
• Compressor and ancillary components installation
• Install piping
• Install electrical, controls and instrumentation

Challenges:
IPS provided 24/7 maintenance services to ANR ensure optimal operation of the compressor station. This relationship was formed over a several year period and IPS took on more and more maintenance responsibilities over time.

IPS
N/A Delivery Method
Year to Year Delivery Method
Maintenance Service Agreement Delivery Method
N/A Total Construction
N/A Project Cost
N/A Completion Date
Year to Year Project Duration
Maintenance Service Agreement Delivery Method