Project Scope:

Sunoco was required to upgrade its pipeline to meet US Department of Transportation requirements. The pipeline runs from the barge off-loading facility at the Port of Toledo to Sunoco’s tank farm in Oregon, Ohio. IPS upgraded the piping, pumps and offloading stations to meet all DOT protocol and requirements.

 

Challenges:

The Sunoco pipeline runs thru the Sunoco refinery in Oregon Ohio. All repairs to the pipeline were required to be made in conjunction with the Sunoco operational permitting processes. This includes daily permits for all hot work and enhanced safety protocol.

IPS
$800,000 Total Construction
N/A Project Cost
6/2012 Completion Date
6 MONTHS Project Duration
Design Bid Build Delivery Method