Project Scope:

In 2007 Sunoco implemented a Naphtha Simplification project, requiring a 6-week plant outage. IPS was hired to manage the turn-around project and performed over 22,000 man-hours during this time. Staff included 30 craft per shift and 11 management staff including general foremen, project managers, superintendents, time keepers, clerks, QA/QC, safety, and document control.

The Scope of Work involved installation of project tie-ins, equipment installation, re-work of existing piping systems, all electrical and re-tray of existing towers. IPS was responsible for full QA/QC services including all NDE inspection, testing, and repair stamp.

Sunoco owns and operate four refineries located in Philadelphia, PA; Marcus Hook, PA; Westville, NJ; and Toledo, OH. These refineries have a combined crude oil processing capacity of 825,000 barrels per day.

Sunoco’s refining and supply business manufactures refined products, primarily gasoline, diesel, jet fuel and residual fuels, as well as commodity petrochemicals.

$3mil. Total Construction
$3mil. Project Cost
N/A Completion Date
6 Project Duration
Cost plus fixed fee Delivery Method

Project Scope:
IPS and ANR Pipeline negotiated a Master Service Agreement for the maintenance and improvement of site facilities, boilers and piping at the ANR Defiance compressor station.
Specific projects include:
• Compressor and ancillary components installation
• Install piping
• Install electrical, controls and instrumentation

Challenges:
IPS provided 24/7 maintenance services to ANR ensure optimal operation of the compressor station. This relationship was formed over a several year period and IPS took on more and more maintenance responsibilities over time.

IPS
N/A Delivery Method
Year to Year Delivery Method
Maintenance Service Agreement Delivery Method
N/A Total Construction
N/A Project Cost
N/A Completion Date
Year to Year Project Duration
Maintenance Service Agreement Delivery Method

Ready to get started?