Project Scope:

Sunoco Logistics owns and operates a logistics business consisting of a geographically diverse portfolio of complementary crude oil, refined products, and natural gas liquids pipeline, terminalling and acquisition and marketing assets which are used to facilitate the purchase and sale of crude oil, refined products, and natural gas liquids.

IPS was contracted to upgrade terminals along their Allegany Access pipeline from Toledo, OH to Pittsburgh, PA. The scope of work included modifications to existing piping, replacement of control valves, inline instruments, installation of 2,000 HP products pumps, ethane tank installations, high voltage substation installation and modifications to the terminal control systems. IPS also excavated concrete, poured foundations, performed structural steel and site enhancement work to support the terminal upgrades. These upgrades and repairs increased the pipeline production, pumping capabilities and terminal throughput. IPS did work on many of the Sunoco sites in Ohio including Hudson, Mogador, Fostoria, Cedar Point, Toledo, Pemberville, Rawson and Willard.

Challenges:

Total Construction:  $100 million

Project Cost:  $18 million

Completion Date:  August 2015

Project Duration:  18 months

Delivery Method:  General Contractor

IPS was able to make the upgrades and repairs to all of the terminals concurrently while keeping the Sunoco sites fully operational so they could continue to meet the demands of their customers.

$100mil. Total Construction
$18mil. Project Cost
8/2015 Completion Date
18 Project Duration
General Contractor Delivery Method

Project Scope:
IPS and ANR Pipeline negotiated a Master Service Agreement for the maintenance and improvement of site facilities, boilers and piping at the ANR Defiance compressor station.
Specific projects include:
• Compressor and ancillary components installation
• Install piping
• Install electrical, controls and instrumentation

Challenges:
IPS provided 24/7 maintenance services to ANR ensure optimal operation of the compressor station. This relationship was formed over a several year period and IPS took on more and more maintenance responsibilities over time.

IPS
N/A Delivery Method
Year to Year Delivery Method
Maintenance Service Agreement Delivery Method
N/A Total Construction
N/A Project Cost
N/A Completion Date
Year to Year Project Duration
Maintenance Service Agreement Delivery Method