Project Scope:

Midwest Terminal, in order to meet US Department of Transportation requirements, needed to upgrade its pipeline encasements to provide an approved secondary containment for the pipeline. The pipeline improvement ran between Midwest Terminal’s barge and rail offloading areas at the Port off Toledo. IPS performed this DOT piping upgrade work.

Additionally, IPS constructed an LPG Rail to truck trans-loading facility. IPS self-performed all equipment sets, structural steel, piping and electrical. The equipment set included the compressor skid and all associated pumps.

 Challenges:

Midwest Terminal’s pipeline is in an active port facility. There are heightened security requirements at this port facility. IPS provided trained and certificated employees that meet all Department of Homeland Security requirements.

IPS
$500,000 Total Construction
N/A Project Cost
6/2014 Completion Date
2 Project Duration
design bid build Delivery Method

Project Scope:
IPS and ANR Pipeline negotiated a Master Service Agreement for the maintenance and improvement of site facilities, boilers and piping at the ANR Defiance compressor station.
Specific projects include:
• Compressor and ancillary components installation
• Install piping
• Install electrical, controls and instrumentation

Challenges:
IPS provided 24/7 maintenance services to ANR ensure optimal operation of the compressor station. This relationship was formed over a several year period and IPS took on more and more maintenance responsibilities over time.

IPS
N/A Delivery Method
Year to Year Delivery Method
Maintenance Service Agreement Delivery Method
N/A Total Construction
N/A Project Cost
N/A Completion Date
Year to Year Project Duration
Maintenance Service Agreement Delivery Method

Ready to get started?