Project Scope:

Premcor/Husky Energy selected IPS to serve as the General Contractor responsible for construction of the Cat Gas Hydro Treater at their Lima, Ohio facility.

IPS self-performed all piping, steel erection and electrical services including installation of equipment and modules, towers, exchangers, heaters, and structural work.

Challenges:

Since the project was designed concurrent with construction, IPS was able to work closely with the lead design firm to ensure that construction and design could proceed in a logical, timely, and cost effective manner. The project schedule was maintained through a cooperative approach at the project team level with an eye toward solving problems in the field prior to their occurrence. However, when problems were identified in the field they were immediately attacked and solved.

$38mil. Total Construction
N/A Project Cost
1100acres Facility Size
2006 Completion Date
18 MONTHS Project Duration
bid build Delivery Method