Project Scope:

The Troy Energy Power Plant is a natural gas-powered electrical generation facility that produces 688 MW of power, which it sells to utility companies at peak demand times.

IPS served as the General Contractor for the new construction of the single-cycle peaking plant in Luckey, Ohio. The project involved the installation of (4) GE Frame 7 Turbine Generators (172 MW each).

IPS was responsible for laying concrete foundations, installing underground piping and electrical systems, BOP piping, BOP electrical, inlet exhaust duct system, fire protection systems, installation of all centerline equipment, centerline piping and electrical, centerline fire suppression system, instrumentation, high voltage duct, calibration, operation, and maintenance building construction.

$234mil. Total Construction
$36mil. Project Cost
N/A Completion Date
12 MONTHS Project Duration
design Bid buildDe Delivery Method

Ready to get started?

Contact Us today