Project Scope:

Single engine expansion

Install owner-provided CAT 3520 landfill gas generator set into exisiting power plant, currently running 3 other CAT 3520’s.  Also install owner-provided exhaust structure and switchgear room.

Challenges:

Project site, already having three generators inside the building, was very space-restricted.  Also, cabling for switchgear building and incorporation into station electrical scheme was very challenging.

IPS
$750,000 Total Construction
$2,000,000 Project Cost
No expansion Facility Size
6/2017 Completion Date
5 MONTHS Project Duration
Lump Sum Delivery Method