Project Scope:

Miceli Dairy, the second largest ricotta cheese manufacturer in the United States, awarded IPS a $13.38 million design and build contract to expand their processing facility and construct a Visitor Center for entertaining clients and product demonstrations.

Work on the project involved construction of a 41,000 SF plant expansion of Miceli’s current facility to include employee lockers rooms, a break room, maintenance facility, dry storage, coolers, freezers, and loading docks.

The project also included construction of a 6,500 SF expandable Milk Unloading building and an 8,500 SF Visitor Center with Bridge to the main production facility. Site work included over $300,000 of soil remediation and the construction of new infrastructure including new primary power and site water retention.

Challenges:

The existing facility needed to remain fully operational throughout construction in order to meet product demands. IPS developed a comprehensive phasing plan with our schedule that included turning over various components to the owner as they were finished.
Multiple trades were scheduled to complete work concurrently throughout the facility. The project finished on time without any interruption to operations.

$13.38Mil. Total Construction
$13.38Mil. Project Cost
41,000SF Facility Size
8/2012 Completion Date
15 MONTHS Project Duration
Bid Build Delivery Method