Project Scope:

IPS was contracted to demo and relocate the DSI unit. Ultimately, adding a water drain-off to Ribbon Blenders 5 & 6 and to update the Starch System for Ribbon Blenders 5 & 6 and to add a supply from Ribbon Blenders 9 & 10 to the E-Line.  IPS also modified the DSI feed for Blending Kettles 3 & 4 thus modifying the E-Line rigging system. This is first major project for the new GF and PE which will eventually solidify the relationship with CSSC, Project Engineer and build trust for future projects.

Challenges:

IPS met the early completion date as requested by Campbell Soup with little interruption to their demanding production schedule. IPS supplied all of the main equipment and automated valves, which are key components in completing fabrication or installation.

$10mil. Total Construction
$330,937 Project Cost
56Acres under roof Facility Size
3/2015 Completion Date
2 MONTHS Project Duration
bid build Delivery Method