Project Scope:

IPS removed the Mix Tank Discharge pump valves and piping to salvage valves and instruments for relocation. IPS was responsible for all associated piping from the Final Use Tank to the Pre-Blend Mix Tank and the Homogenizer Supply Tank.

Challenges:

Although everything on this project ran smoothly, there were some manpower issues and scheduling matters that led to some challenges. IPS completed the project on time with little interruption to their production schedule and were on budget.

$10mil. Total Construction
$68,118.00 Project Cost
56Acres under roof Facility Size
5/2015 Completion Date
2 MONTHS Project Duration
bid build Delivery Method