Project Scope:

IPS was responsible for installation of all utilities during construction of the North Campus Laboratories, which included both under and above-ground phases.

Underground work involved installation of all sanitary, storm, acid waste, and RO systems.  IPS installed 1,100 lf of pre-insulated glass piping to accommodate the acid waste system.

The aboveground phase consisted of all plumbing, HVAC and laboratory work. IPS installed above ground hot water piping, chilled water piping, acid waste, RO systems, domestic water, specialty gases, laboratory equipment and fixtures.

Challenges:

Installation of the building utilities required working in very tight areas with other contractors above the ceiling and casework rough-ins for the plumbing. In order to accommodate all trades working in the facility, IPS developed a work coordination plan for phasing the installation of ductwork, heating systems, chilled water systems, and plumbing systems. This helped the project to remain on schedule while avoiding any conflict with other trades working in the area.

$12mil. Total Construction
$1.4mil. Project Cost
13,000SF Facility Size
2002 Completion Date
11 Project Duration
bid build Delivery Method

Project Scope:

IPS was contracted by BGSU for this Central Heat Plant to Shatzel Hall Tunnel Restoration project. This included the replacement of the deteriorated Heat Plant Tunnel tunnel top below Thurstin Street and tunnel vault wall, pipe anchoring, and top where the secondary backup steam line enters the tunnel as it turns to the east under the parking lot heading towards Shatzel Hall, replacement of several deteriorated pipe rack supports in various locations throughout the entire tunnel, removal and replacement of up to five tunnel top expansion joints, insulating the pumped and high pressure condensate lines, plus installation of new LED lights and tunnel ventilation kiosks, etc. The utilities were contained within the tunnel system. The high pressure steam and the condensate lines were active during the construction of the tunnel renovation. IPS protected the piping located under Thurstin Ave during the replacement of the tunnel top and the walls in this area when the tunnel top was removed. IPS secured this area from accidental entry with proper protection (i.e. fencing, barricades, and signage) for the duration of the tunnel top replacement.

Challenges:

IPS dealt with the water infiltration and uninsulated piping issues before making any repairs to the tunnel structures. IPS replaced the section of the Heating Plant Tunnel for the portion under Thurstin Street. This tunnel top replacement required the removal of the roadway surface and the subbase located over the tunnel. This work was planned to be done for half of the tunnel at time to limit the disruption to traffic flow and locations and waterproofing to prevent future water infiltration from occurring.

IPS
8/2018 Delivery Method
N/A Delivery Method
Bid Build Delivery Method
$938,800 Total Construction
$ 901,000 Project Cost
8/2018 Completion Date
N/A Project Duration
Bid Build Delivery Method

Ready to get started?

Contact Us today