Project Scope:

The Center for Health Services opened in 1995 to enhance hospital services by providing outpatient primary, selective specialty, and preventive care. The Center offers a wide variety of adult services including internal medicine, surgery, trauma treatment, podiatry, orthopedics, gastroenterology, infectious disease treatment and a full range of women’s health services

IPS was responsible for the HVAC and Plumbing portion of the project. The scope of involved installation of the absorption chiller, cooling tower, chilled water pumps, med gas piping, domestic water, plumbing fixtures, sheet metal, insulation and balancing services.

Challenges:

This fast-track project required completion within 12 months. When construction commenced, the building design was only 75% complete and the mechanical room design was still at the schematic stage with no plan drawings. IPS elected to fabricate the mechanical room piping offsite to allow expedited installation. Coordination drawings were completed by IPS, with input from the electrical and fire protection contractors.

IPS
$12.5mil. Total Construction
$1.2mil. Project Cost
55,000SF Facility Size
1995 Completion Date
12 Project Duration
bid build Delivery Method

Project Scope:

IPS was contracted by BGSU for this Central Heat Plant to Shatzel Hall Tunnel Restoration project. This included the replacement of the deteriorated Heat Plant Tunnel tunnel top below Thurstin Street and tunnel vault wall, pipe anchoring, and top where the secondary backup steam line enters the tunnel as it turns to the east under the parking lot heading towards Shatzel Hall, replacement of several deteriorated pipe rack supports in various locations throughout the entire tunnel, removal and replacement of up to five tunnel top expansion joints, insulating the pumped and high pressure condensate lines, plus installation of new LED lights and tunnel ventilation kiosks, etc. The utilities were contained within the tunnel system. The high pressure steam and the condensate lines were active during the construction of the tunnel renovation. IPS protected the piping located under Thurstin Ave during the replacement of the tunnel top and the walls in this area when the tunnel top was removed. IPS secured this area from accidental entry with proper protection (i.e. fencing, barricades, and signage) for the duration of the tunnel top replacement.

Challenges:

IPS dealt with the water infiltration and uninsulated piping issues before making any repairs to the tunnel structures. IPS replaced the section of the Heating Plant Tunnel for the portion under Thurstin Street. This tunnel top replacement required the removal of the roadway surface and the subbase located over the tunnel. This work was planned to be done for half of the tunnel at time to limit the disruption to traffic flow and locations and waterproofing to prevent future water infiltration from occurring.

IPS
8/2018 Delivery Method
N/A Delivery Method
Bid Build Delivery Method
$938,800 Total Construction
$ 901,000 Project Cost
8/2018 Completion Date
N/A Project Duration
Bid Build Delivery Method

Ready to get started?

Contact Us today