Project Scope:

IPS was responsible for the installation of the Mechanical and HVAC systems for the new high school. The following equipment was installed by IPS: (2) 7,000 MBH Boilers, (2) 400-ton Chillers, (13) Indoor Air Handling Units, (4) Computer Room A/C Units, (200) Terminal Units, (6) End Suction Pumps, (15) Inline Circulation Pumps, Unit Heaters and Cabinet Unit Heaters.

The new school is a new building, grades 9-12 that will replace the existing building on the same site. The 225,654 square foot school will have a capacity of 874 and 176 Career Tech students. The old Rogers school was demolished and the area will be converted into parking, athletic field or other campus use. This project was completed in February of 2008.

 

Challenges:

IPS worked with school officials to ensure this aggressive timeline was met and all mechanical and HVAC systems were fully functioning.

$35mil. Total Construction
$5mil. Project Cost
225,654SF Facility Size
2/2008 Completion Date
24 Project Duration
bid build Delivery Method

Project Scope:

IPS was contracted by BGSU for this Central Heat Plant to Shatzel Hall Tunnel Restoration project. This included the replacement of the deteriorated Heat Plant Tunnel tunnel top below Thurstin Street and tunnel vault wall, pipe anchoring, and top where the secondary backup steam line enters the tunnel as it turns to the east under the parking lot heading towards Shatzel Hall, replacement of several deteriorated pipe rack supports in various locations throughout the entire tunnel, removal and replacement of up to five tunnel top expansion joints, insulating the pumped and high pressure condensate lines, plus installation of new LED lights and tunnel ventilation kiosks, etc. The utilities were contained within the tunnel system. The high pressure steam and the condensate lines were active during the construction of the tunnel renovation. IPS protected the piping located under Thurstin Ave during the replacement of the tunnel top and the walls in this area when the tunnel top was removed. IPS secured this area from accidental entry with proper protection (i.e. fencing, barricades, and signage) for the duration of the tunnel top replacement.

Challenges:

IPS dealt with the water infiltration and uninsulated piping issues before making any repairs to the tunnel structures. IPS replaced the section of the Heating Plant Tunnel for the portion under Thurstin Street. This tunnel top replacement required the removal of the roadway surface and the subbase located over the tunnel. This work was planned to be done for half of the tunnel at time to limit the disruption to traffic flow and locations and waterproofing to prevent future water infiltration from occurring.

IPS
8/2018 Delivery Method
N/A Delivery Method
Bid Build Delivery Method
$938,800 Total Construction
$ 901,000 Project Cost
8/2018 Completion Date
N/A Project Duration
Bid Build Delivery Method

Ready to get started?

Contact Us today