Project Scope:

In 2002 Toledo Public Schools began a $650 million, multi-year program to renovate or rebuild 40 school buildings. Pickett Academy was the final building to be constructed as part of this program.

IPS was contracted to provide installation of the complete mechanical systems at the school including HVAC, fire protection, utility piping, and project controls. IPS procured and installed boilers, chillers, pumps, air handling units, roof top units, and exhaust fans. Additional services provided by IPS include: testing and balancing, chemical treatments, and temporary heating during winter months.

Challenges:

The project required fast-track scheduling in order to ensure the facility was fully operational by the start of the 2012-2013 school year. Multiple trades were scheduled to complete work concurrently throughout the facility. IPS coordinated work with other trade contractors in order to avoid any interference or equipment relocation that might be caused by overlapping work areas.

$7.5mil. Total Construction
$1.1mil. Project Cost
75,000SF Facility Size
4/2012 Completion Date
9 Project Duration
bid build Delivery Method

Project Scope:

IPS was contracted by BGSU for this Central Heat Plant to Shatzel Hall Tunnel Restoration project. This included the replacement of the deteriorated Heat Plant Tunnel tunnel top below Thurstin Street and tunnel vault wall, pipe anchoring, and top where the secondary backup steam line enters the tunnel as it turns to the east under the parking lot heading towards Shatzel Hall, replacement of several deteriorated pipe rack supports in various locations throughout the entire tunnel, removal and replacement of up to five tunnel top expansion joints, insulating the pumped and high pressure condensate lines, plus installation of new LED lights and tunnel ventilation kiosks, etc. The utilities were contained within the tunnel system. The high pressure steam and the condensate lines were active during the construction of the tunnel renovation. IPS protected the piping located under Thurstin Ave during the replacement of the tunnel top and the walls in this area when the tunnel top was removed. IPS secured this area from accidental entry with proper protection (i.e. fencing, barricades, and signage) for the duration of the tunnel top replacement.

Challenges:

IPS dealt with the water infiltration and uninsulated piping issues before making any repairs to the tunnel structures. IPS replaced the section of the Heating Plant Tunnel for the portion under Thurstin Street. This tunnel top replacement required the removal of the roadway surface and the subbase located over the tunnel. This work was planned to be done for half of the tunnel at time to limit the disruption to traffic flow and locations and waterproofing to prevent future water infiltration from occurring.

IPS
8/2018 Delivery Method
N/A Delivery Method
Bid Build Delivery Method
$938,800 Total Construction
$ 901,000 Project Cost
8/2018 Completion Date
N/A Project Duration
Bid Build Delivery Method

Ready to get started?

Contact Us today