Project Scope:

Sunoco Logistics Partners LP provides storage and distribution services for refiners and other large transporters of petroleum products. In 2014, the firm announced plans to add 160 miles of underground pipeline in Ohio and Pennsylvania in order to deliver petroleum from expanding production areas and refineries to markets where demand exists.  Sunoco Logistics contracted IPS to provide a power distribution solution to fit the needs of the expanded system.

IPS self-performed all electrical and civil work to construct the substation.  Work on this 69kv-4.16 kv, 3-Phase substation included installation of a 69 kv/7000 kva 3-phase transformer, all wiring, transformer containment, ground grid, structural steel, fusing, lighting, arrestors, and civil work.

Challenges:

During the project, IPS worked closely with Edison to schedule the high voltage tie-ins. Engineering discrepancies were handled through the RFI process. IPS completed the project on time and within budget

IPS
$5.68MIL. Total Construction
$710K Project Cost
10 Acres Facility Size
6/2015 Completion Date
18 Project Duration
Bid Build Delivery Method

Project Scope:

IPS built and owns 1 MW solar array located at Collins Park Water Treatment Plant. IPS sells 100% of the power produced at the facility to the water treatment plant. The facility was constructed as part of a public/private partnership to provide the water treatment plant with renewable energy over the next 25 years. The project also cuts down on electricity costs considerably for the City of Toledo.

IPS planned, financed and built the facility. During construction, IPS managed the engineering and procurement of the facility. IPS subcontracted the civil and structural components as well and self-performed the electrical work.

Challenges:

This was a fast track construction phase that was completed in 3 months in order to begin production at a time of high energy demand. Construction was impeded by an unusually wet spring, but the facility was completed on time and on budget.

8/2011 Delivery Method
9 Delivery Method
EPC Delivery Method
$5MIL. Total Construction
$5MIL. Project Cost
8/2011 Completion Date
9 Project Duration
EPC Delivery Method

Ready to get started?

Contact Us today