Project Scope:

Sunoco Logistics Partners LP provides storage and distribution services for refiners and other large transporters of petroleum products. In 2014, the firm announced plans to add 160 miles of underground pipeline in Ohio and Pennsylvania in order to deliver petroleum from expanding production areas and refineries to markets where demand exists. Sunoco Logistics contracted IPS to provide a power distribution solution to fit the needs of the expanded system.

IPS self-performed all electrical and civil work to construct the Pemberville substation. Work on this 34.5kv-4.16 kv, 3-Phase substation included installation of a 34.5 kv/7000 kva 3-phase transformer; all wiring; grounding (deadhead, grid, CT & PT metering stands, fencing, ground mats, hydronic piping mains); transformer containment; and civil work.

Challenges:

During the project, IPS worked closely with the local utility to schedule the high voltage tie-ins. The project required precise coordination to complete the work on the substation and transmission lines, and to ensure scheduled outages were kept to an absolute minimum. IPS successfully completed the project on time and within budget.

IPS
$3 Mil. Total Construction
$500 K Project Cost
2/2015 Completion Date
6 MONTHS Project Duration
Bid Build Delivery Method

Ready to get started?

Contact Us today